Skip to Content

Financial Planning Data Transfer from PS to PPM

fin-data-transfer.pngppm-data-transfer.png

Hello Experts,

Please advise if this configuration (Financial Object Link Types for Hierarchical Processing) is required for data transfer from PS to PPM.??

My requirement is to get the reporting in below manner.
e.g.
Material 200000
Services 255000
Travel cost 30000
Overhead 4000000

what would difference come if I select hierarchical processing for mentioned projects like.

e.g.

0INMPSPD
0INMPSWBS
0NETWORK
0NETWORKACT
0PROJECTDEF
0RPMFINETACTEL
0RPMFINETHIERAR
0RPMFINETWORK
0RPMFINETWRKACT
0RPMFINWAHIERAR
0RPMFIPROJECT
0RPMFIWBSELEMNT
0RPMFIWBSHIERAR
0RPMPSNETWORK

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Feb 10 at 10:36 AM

    Hi Gaurav,

    Are you looking to build a report or trying to transfer data from PS to PPM Item financial planning?

    Regards,

    Ravi

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 12 at 05:10 AM

    Hi Ravi,

    Trying to transfer data from PS to PPM item financial planning.

    Regards

    Gaurav Ahuja

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 13 at 05:27 AM

    Hi Gaurav,

    Then you do not need Object link types of Hierarchical processing. You just need to ensure following object link is active and correct RFC destination of ECC system is updated.

    0RPMPSPROJECT

    And ensure you object link, PS project to Portfolio item before running the transfer report.

    Regards,

    Ravi

    Add comment
    10|10000 characters needed characters exceeded