Main Order TECO when Sub-Order is open

former_member546319
Contributor
0 Kudos

Dear All,

I just wanted to clarify if we can do TECO of Main Order when Sub-Order is open? If we can control this using any settings.

Presently it is not allowing to do TECO of Main Order as long as Sub-Orders are open.

Regards,

MLN Prasad

Accepted Solutions (1)

Accepted Solutions (1)

former_member1107731
Contributor

The Main Order Cannot be set to TECO If any sub order exists for the Main Order and have not been completed. When Teco-ing the main order without having completed the sub order the system would show you the following message: Open Sub Orders Exist for the Order (IW 189). To avoid this for example if you want to allow the Technical Completion of the Main Order with its sub orders as open, then

Go To SPRO-->Plant Maintenance -> Maintenance and Service Processing-> Maintenance and Service Orders-->Message Control

Here look for the message IW 189 and change its category from E (Error) to W (Warning) or No Message. This would solve your problem.

Answers (1)

Answers (1)

Former Member
0 Kudos

Prasad,

In standard the Main order can be set to TECO even if the sub order is open.User exit on save of the order , can be one of the locations to place a custom check. This cannot be accomplished automatically through user status(Since these are different objects), unless you have a custom program to accomplish the same.

Regards

Narasimhan