SAP PPM - WBS not getting created in PS from Portfolio project

Hi,

I am trying to create project in SAP PS from portfolio project, I am able to create Project definition and 1st level WBS from Portfolio project , however structure is still not created from task.

I have done accounting integration.

Any ideas what I am missing.

Regards

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 10 at 08:44 AM

    Hi Rajeev,

    What have you provided in Controlling level of accounting integration in 'Define controlling scenario'? If you have provided 1, then only 1st level objects are created. You may have to select the level according to the structures expected in PPM project.

    Regards,

    Ravi

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 10 at 11:20 AM

    Hi Ravi

    I have added 99 levels.

    But still only wbs gets created.

    any reason for the behavior??

    Regards

    RAJIV