Business content implementation timeline

Former Member
0 Kudos

Hello folks,

Trying to get an idea of timeline to plan for implementing standard business content for the new G/L functionality and Asset accounting. Assume a brand new SAP BI install EHP3 and no customization. Will appreciate any guidelines to consider for this.

Thanks!

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

No takers!

Former Member
0 Kudos

No customization? Standard guidance is that business content only gets you 10-20% of the way....

Also still many variables...performance optimization...for instance do you use FI_GL_10 or FI_GL_12...same content but different method of delta extraction and big concern depending on requirements....Also do you plan to convert business content to follow current best practice? LSA/EDW approach? Or leave it in 3.x format? Queries? Implementation of MultiProviders? Time to design security roles and validate? Bex web or simply analyzer? Are you wanting to know end to end time for no customization and integration testing with users, and time to go-live? Or just straight content activation time in development only?

The straight up content activation time with no customization, testing, etc. is the smallest part of the project, but is still significant depending on which InfoProviders you choose, etc.

You can stand it up in a couple of weeks...but you'll spend months making it useful.