Dear exeperts,
Is is possible to insert a Ref Operation Set after a routing has been inserted in a prod order? I am getting the error Message no. CO892 which I can't resolve. I know for service orders there is not such constraint.
Thanks in advance to share your wisdom!
Francois P.
Ref. operation set 50000148 is not valid according to the selection conditions
Check why the reference operation set does not meet the selection conditions:
1. Is it valid on 2010/07/16? OK
2. Is lot size within its validity area? OK
3. Is the selection ID for routing selection (Customizing: order type- dependent parameters) of a type that allows reference operation sets to be selected? OK parameter routing selection = 5
4. If the reference operation set has a change number, is it valid for production on 2010/07/16? OK