Hello Everyone

My question is related to forecast finshed date (FFD) from confirmation.

I have made a project with 2 activities A & B in FS relation. When i partially confirm activity A, system ask forcast finished date though it is not mandatory. I have following 2 questions:

1- Can system suggest me forecast finished date after partial confirmation ?

2- If I dont put a date in FFD, system is calculating certain earliest finished date after a scehdule run. Can anyone advise how system is calculating this finish date ?

Regards,

Kashif