MRP run to combine pr's for particular component on monthly basis (project)

Hi, wants mrp run to combine the qty of same component which is the bom item for different sales orders (project orders). also required to know the qty tracebility against sales order or project order. for that we maintained MB lot size and 1 in ICI in mrp4 view of the component material master. wants system to combine the qty of same component and generate 1 pr (purchase requisation) on monthly basis. please advise any user exit or badis or development is possible.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 08, 2010 at 10:14 AM

    Hi

    In OMI4 , Lot sizing procedure , insert 1 in NO. of periods field so that u will get only one consolidated requirement for a month.

    S Anil

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.