Myclient is doing MFBF he maintaining 4 PV for each part number since he s operating n 4 work centres.Here he wants to know in which PV he did a production confirmation for particular period or day.

P.Srinivasan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Solved

Former Member
0 Kudos

Hi Shrinivasan,

Use report MCP6 or MCP8

Put here -Plan PV ,Work center ,And date range

Regards

Girish

Former Member
0 Kudos

Hi Girish,

Girish i can able to see whether PV or matererial wise only,shall i see Material,PV and quantity in one column in the output of the report.