Purchase order

Former Member
0 Kudos

Hi SAP Experts,

As per my knowledge when we are doing Purchase Order,no documents(Accounting,Controlling and Profit center) will get generated.But while creating Purchase Order,we enter cost center.i.e account assignment "K". My question is that is there any way to generate a controlling document at the time of creating Purchase Order.

Thanks in advance,

Ajay Chillarige.

Accepted Solutions (1)

Accepted Solutions (1)

RahulGoyal
Active Participant
0 Kudos

However, you can have commitment update in Controlling when PO is created. Is that the purpose of looking controlling document while PO creation? If you want to monitor, lets say capital / expense commitments at month end, you can activate commitment update at PO creation. If that is the purpose, activate commitment update at controlling area level as one for individual cost object.

Hope it helps.

Thanks.

Rahul

Former Member
0 Kudos

Thank you .I have done as per your instructions and now i am able to see CO Commitments documents.

Ajay Chillarige.