the actual date is not transferred from the (PS) milestone

102 Views

Hello ,

In an order with header billing plan dates that are value-based, the actual date is not transferred from the Project System (PS) milestone, even though the actual date of the assigned milestone was changed via transaction CJ20N.

We are repeatedly facing this error , I have applied Note number 1395078 but still once in a while I am still facing the issue

Regards

Muralidharan.S