Hi,

I have created a substitution rule at line item level (callup point-2).

But there is a substitution rule already exist and active at callup point-2 .

We cant able to create new entry for this substitution rule for active at OBBH.

How can i activate both substitution rules at a time in same company code?

Regards

Surya

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 06, 2010 at 09:08 AM

    Hi,

    If you want to have another substitution rule at the same call point, you can add another step within the existing Substitution.

    Regards,

    Mike

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 06, 2010 at 09:07 AM

    Hi,

    You can create a new step in the substitution rule which already exist, and activate the same for your company code, in case you have created a seperate substitution rule, you can activate both at the same time in OBBH

    regards

    Vikash

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.