Hi SAP Gurus!
How does budget checking work in the Service Entry Sheet?
1. When I create the PO, the total value is committed in the budget, right?
2. When I create the unaccepted service entry sheet, the total value should still be in the committed state. Is this correct?
3. When the service entry sheet is accepted, the total value should be in the actual state in budget checking, right?
Hope to hear from you guys soon!
Thanks in advance!
Hi,
1) Yes, Correct.
2) Yes, Correct.
3) Yes, absolutely right.
Your three points are 100 % correct.
Hope, now you are clear.
Regards,
K.Rajendran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
From PR to PO the cost reflects as commitment costs in PS projects .. once SES is accepted commitment gets converted to Actual Costs ...
Now I think SES is posted against Maintenance Order , So you can have PS Budgeting for MO by assigning WBS element in Additional Tab of MO ..,
You need to do config under SPRO --->PS --->Costs --->Budget
At the same time look into the config in OPSV which controls how the MO costs should reflect in PS ..
regrds
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.