Hi,

The customer asked me if it is possible in WBS control of availability , to check the budget in relation of individual cost items.

I thought about a WBS structure to create a WBE as a container of Primary cost, later Planning the WBS.

When checking availability works, the controll will be more dettailed respect a total control.

Is there a way to optain this kind of control more easyly?

Thank you for attention.

Kind regards.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Posted on Jul 05, 2010 at 06:29 PM

    Budget control is done on values in the WBS element and not on cost elements

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 06, 2010 at 09:57 AM

    Hi,

    As Virendra said budgeting is done for values on the WBS elements and not for the cost elements. In addition to this there is an option wherein you can exclude certain cost elements for which you dont require budgeting.

    Regards,

    Gokul

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 06, 2010 at 08:04 PM

    tanks a lot

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.