cor1 release prcess order

Hi In trying to relaese the Process order i have this message:

"no control data maintained for checking group 02 and checking rule ZI"

i have checked in OPJJ, VOV6; OPJK,OVZ3 and all is maintained.

am i missing something?

thanks

C.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 05, 2010 at 02:09 PM

    problem solved

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 05, 2010 at 02:14 PM

    Dear

    Order release can be rejected for multiple availability checks 1) Non - Availability of Component stock 2) Non-Availability of PRT stock 3) Non-Availability of Capacity for the required resources. Check the transaction OPJK for the plant/ order type combination for business function "2".Go to Tcode OPJK For your order type check the settings What is the set up ?

    There in the material release option you have 3 options

    1.User decides on release if parts are missing

    2.Release permitted despite missing parts

    3.No release if parts are missing

    Keep -2 so that even if you have missing parts it will be released

    Check and revert back

    Regards

    JH

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.