Dear All,
I have the following scenario:
1 - GI of a delivery in period 1
2 - Reversal of movement in period 2
3 - 2nd GI in period 2
3 - User now wants to reverse it (again) in period 1
My experience is that this is not possible because from the moment the batch stock was received in period 2, SAP sees it as existing from period 2 only. So when trying to reverse it in period 1 system rejects reversal.
In the past my solution has always been to reverse GI in period 2, write off stock, re-create batch + stock in period 1 and re-GI in correct period.
However this may be an outdated approach and I was wondering if anyone knows of a different solution.
The process is WM as well.
Thanks for letting me know
Kind regards
Kikas