Re-scheduling Process Orders

Dec 01, 2016 at 10:06 PM

17

avatar image

Hello,

We are using basic scheduling for planned orders (based on in house prod. time). In order to maintain the basic dates when converting planned to process orders, we selected the option do not adjust basic dates and deselected the automatic scheduling in OPUZ. The process works fine until this point. However, when the planner needs to re-schedule a process order by deleting the end date and updating the starting date on Forward scheduling, the sytem does not re-calculate the end date based on the in-house prod time. Any suggestion on how to accomplish this requirement?

pp
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

0 Answers