Hi All,
I am unable to change the Finish date for the PO. I am attempting to change the Finish date to 07/29/10, but it reverts back to 06/29/10.
Actually the start date now is 11.05.2010 and end date in 29.06.2010.In the sequence of operations one operation started on 11.05.2010 and ended on 12.05.2010.After that the operation started on 28.06.2010 and ended on 29.06.2010.
Now i m not able to re-schedule this order bcoz it says "Start date is in the past".
Please help.
Thanks & Regards,
Ameya K.