SNP PPM does not contain resource

nitin_thatte
Contributor
0 Kudos

Hi,

We are using PP-PI in R/3. We have CIFed PPM to APO.

The transferred PPDS PPM contains Operation 10 and phase 20 (indicating that 10 is superordinate operation).

We are converting it to SNP PPM with lot size margin.

The PPM is generated successfully but the SNP PPM does not carry the primary resource.

What should be done for this?

Thanks

Nitin Thatte

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Nitin,

Is the resource is present in active integration model?

Also check your settings in CFC9 transaction. Check

the application log generated during conversion.

Regards

R. Senthil Mareeswaran.

nitin_thatte
Contributor
0 Kudos

Hi.

Thanks for the replies.

The Resource is single mixed

Resource is SNP relevant

Resource is there in active int model. The resource appears in the phase of PPDS PPM. It is vanishing while converting to SNP PPM.

Thanks once again.

digambar_narkhede
Contributor
0 Kudos

Hi Nitin,

As you mentioned that all required settings are in place but still generated SNP PPM does not contain resource,then the only possibility is that the Routing Operation do not have any consumption(standard value) maintained for the reqd base qty and due to this even though the PPDS PPM is generated it will have zero activity duration and also Bucketed resource consumption (variable and fixed) in PPDS PPM would be zero .

And hence as there is no relevance of resource for planning and scheduling in lon term it is not appearing in SNP PPM.

Could you please check n correct the consumption (standard value=hrs) maintained in routing and reCIF the PPDS PPM and then try for SNP PPM.

This will definitely resolve your issue as I did face same issue.

Regards,

Digambar

nitin_thatte
Contributor
0 Kudos

In PPDS PPM I am able to see 0.6 hr as variable resource consumption.in mode.

One more information....... If I transfer it as SNP PDS instead of PPM, I am able to see the resource in PDS.

So it seems the problem lies purely in conversion of PPDS PPM to SNP PPM.

Edited by: Nitin Thatte on Jun 29, 2010 2:38 PM

Edited by: Nitin Thatte on Jun 29, 2010 2:40 PM

Former Member
0 Kudos

Hi,

Please refer to OSS note 481906 u2013 SNP-PP/DS Integration ( Documentation).

This may help.

Regards

Datta

digambar_narkhede
Contributor
0 Kudos

Hi Nitin ,

Can you please check the activity duration for that PPDS PPM and also the activity type appearing in SNP PPM (if it is a 'W' Queue time instead of 'P' produce of that PPDS PPM) generated from PPDS PPM?

Regards

Former Member
0 Kudos

Hi Nitin,

SNP PPM requires variable bucket consumption to create activity on resource. This value comes from PPDS PPM. Now this value is not assigned automatically when you CIF PPDS PPM. You have to maintain user exit or for testing enter value in variable bucket consumption (In PPDS PPM, in mode tab, double click on resource and check column for variable bucket consumptio). Once you maintain this value and then convert PPDS PPM, then resource and same bucket consumption value will appear in SNP PPM.

Bets regards,

Vaibhav

nitin_thatte
Contributor
0 Kudos

I am able to see variable consumption in the mode of PPDS PPM

Former Member
0 Kudos

It should be variable bucket consumption and not variable continuous consumption. If you mean same then I have not seen any other cause of such error.

Best regards,

Vaibhav

nitin_thatte
Contributor
0 Kudos

thanks for the reply.

It is indeed continuous consumption. However I have transferred many PPMs in the past (on other sites) without any user exit. Don't know why this problem?

I will explore more.

Former Member
0 Kudos

Hi,

Today i also faced the same issue. But when i did the consistency check for the PPDS PPM i could see there are some errors.

Once rectified the errors , i could see the SNP PPM having the resource.

Request you to check the consistency of PPDS PPM.

Thanks,

nandha

nitin_thatte
Contributor
0 Kudos

can u tell name of user exit?

Former Member
0 Kudos

Hi,

Dont remember exactly...try this...take help of ABAP consultant

User exit :- EXIT_CIFPPM01

Function Module :- EXIT_SAPLPGS1_001

Best regards,

Vaibhav

digambar_narkhede
Contributor
0 Kudos

Hi Nitin ,

Please refer SAP Note 737991 - SNP PPM generation: Resources are not generated if it helps .

Regards,

Digambar

Former Member
0 Kudos

Hi Nitin,

You might have probably already this checked .

Is the resource you expect to have in the SNP PPM is single mixed or multi-mixed ?

Regards

Datta

Former Member
0 Kudos

Is it SNP Relevant resource?

Regards,

nandha