ATP check config

Hello Experts,

We have a new requirement. They have two plants A and B in different locations. Currently all orders come to plant A and Plant B will be a new plant. Once Plant B is live, requirement is that once customer sends schedule to Plant A, there should be ATP check in Plant A and if there is no stock available in Plant A then ATP check should be done in Plant B and even if Plant B does not have immediate stock then new delivery date should be proposed from Plant A only.

I know we can do ATP check in one plant but is there any config available in standard SAP to do ATP check across multiple plants in same company code.

Thanks,

Karan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Dec 02, 2016 at 08:54 AM

    With standard configuration, this is not possible assuming that APO is not integrated. You can try with BAPI_MATERIAL_AVAILABILITY

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 05, 2016 at 03:16 PM

    Hi Karan,

    you can achieve your requirement with the Rules-Based Availability Check (RBA) functionality in SCM APO as described here:

    https://wiki.scn.sap.com/wiki/pages/viewpage.action?pageId=117506886

    and

    http://help.sap.com/saphelp_apo700_ehp03_on_erp/helpdata/en/8f/43c95360267614e10000000a174cb4/frameset.htm

    Regards,

    Tibor

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 17, 2017 at 09:15 AM

    Hi Karan,

    THis is possible using RBA functionality of GATP as Tibor highlighted above.(Assuming you are using APO system).

    You can use Location substitution to check ATP at both locations and also you can decide where(Plant A or Plant B) to put remaining unfulfilled requirement.