Scheduling maintenace order

HI

fds

while creating maintenance work order. scheduling is not carried out it is giving the following msg.

Scheduling log does not contain any entries

Message no. C7119

i have maintain all the scheduling parameters , so scheduling should be carried out but it is not happening, can anyone plz tell me wht may be the problem.

Edited by: nishj.s on Jun 28, 2010 11:12 AM

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Jun 28, 2010 at 09:36 AM

    Hi,

    What kind of scheduling you are doing? What kind of plan either cycle plan or strategic plan? Can you please elaborate?

    Regards,

    Maheswaran.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      The order would have been scheduled properly based on the config and input parameters.What makes you think that the order should have scheduling issues?

      Regards

      Narasimhan

  • avatar image
    Former Member
    Jun 29, 2010 at 03:40 AM

    Hi,

    It would be better if you could explain more about that with the data you used like following:

    1. What are the Maintenance Packages

    2. What is the formula

    Please elaborate completely.

    Regards,

    Maheswaran.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 29, 2010 at 06:53 AM

    Hi Nishj,

    Besides the data like package, scheduling parameters etc,Also mention the details of the error by double clicking on the log and paste it in the thread for better understanding.

    Also check and mention the Config parameters maintained for that plant from the path

    IMG >Plant Maintenance and Customer Service >Maintenance and Service Processing >Maintenance and Service Orders >Scheduling-->Set Scheduling Parameters.

    Also check and mention the parameters maintained in the Capacity tab in the Work center

    Check if "relevant to finite scheduling" checkbox is checked or not for that work center for the plant

    Also mention the other parameters for planning details in this case i.e other check boxes.

    Regards,

    Manish

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 29, 2010 at 07:32 AM

    nishj.s

    This is a standard message. You often get this message when you manually schedule and order and there are no changes to the current scheduling data.

    Were you expecting any changes to occur?

    PeteA

    Add comment
    10|10000 characters needed characters exceeded