on 06-28-2010 8:34 AM
Dear Friends,
I am trying to create one scenario for campaign planning. I have two products A and B which is being produced on Resource R.
Configuration I have done
1. Campaign profile
2. Strategy profile
3. Optimizer profile with campaign and bottleneck optimization active
Master Data.
Defined respective setup groups in PPM
set up matrix
Defined resource as campaign relevant and assigned setup matrix into it.
Now I have demand of these products. I am running heuristic and creating planned order.
After that I am running heuristic SAP_PCM_CRTwith strategy profile in order to create campaigns
But campaigns are not getting created. I have no clue why it is happening.
or
I run optimizer but still result is same
Please correct me if I m missing something.
Regards,
Pankaj Modi
Hi Pankaj,
Have you created one dummy product and PPM with same resource for this product.
Have assigned this PPM in set up matrix for different set up transistions.
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.