Dates Mismatch of Receipts in RRP3 Elements Tab and ATP Tab

Hi Experts

We recently Implemented GATP with Basic methods which includes Product ATP Check and Allocation Planning in APO.

We are facing following Problems:

1) Dates of Receipts are shifted to one day in ATP tab as well as Product Availability Overview.

eg: If i create Planned Order today i.e 28.06.2010 , system is showing Planned order tomarrow 29.06.2010 in Product Availability Overview and ATP Tab of Product View.

In Elements view Planned Orders are showing correctly.

2) Sales Orders are Visable in ATP Tab and not visable in Elements Tab.The results are same even after running CCR.

Please give your suggestions on my above queries.

Thanks in advance

Thanks & Regards

Roopa

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jun 28, 2010 at 02:34 PM

    Hi APO Experts

    Any Guess on my issue?

    Why system is behaving such?

    Any Help is highly appreciated.

    Cheers

    Roopa

    Edited by: roopa.vaidya on Jun 28, 2010 4:42 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 29, 2010 at 12:00 PM

    Hi Roopa,

    Is the issue happening for all products or only selected? If only selected products,

    then compare the good ones with the error ones

    Also check the category and category group whether they are defined

    properly..

    Run transaction /SAPAPO/ATPQ_CHKCUST and look for any errors

    Please confirm.

    Regards

    R. Senthil Mareeswaran.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 01, 2010 at 07:23 AM

    Hi Roopa,

    Please check whether SAP note 1039555 is applicable to you

    Regards

    R. Senthil Mareeswaran.