on 06-25-2010 1:01 PM
Hi,
I have a problem.
I have activate the Project cash management.
I have run the transaction OPH1 for delection Actual DATA.
I have run the transaction OPH4 for reconstruction actual data for purchase orders.
Ihave run the transaction CJEN for reconstruction info database.
The customizing for the value category is green.
In the report S_ALR_87013573, we display always wrong value , tough line items (CJIA ) is blank.
We have run again the transaction OPH1 for delection Actual DATA, but we display the worng value in the table RPSCO. .
Kindly suggest me the solution.
Best Regards
Federica
hi,
execute the below reports in se38 and after that run cjbn,cjen
RKACOR19-Reconcile between line items and totals records
RKPEP010-Display Project Actual Payment Line Items
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.