on 06-25-2010 5:13 AM
PP Experts,
We have various groups of labour defined as work center in the system.
We have also defined work center catagory as a person.
In no. of individual capacity field we have updated no. of labours in that work center hence the system is
giving me no. of available hours.
Now my requirement is , in over time not all labours are required only few are there. How can map this in the system.
Thanks in advance,
RG
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajiv
HR module need to be integrated with PP for this requirement