Mass change of basic start and finish dates for WO's

Hi Gurus,

Is there a functionality to mass change basic start and finish dates for WO's without having to individually go into the WO and change it.

I pull all my work orders due for a particular month using IP24, and I want to change the Basic start of say 100 WO's to the first day of the month and basic finish to the last day of the same month and was wondering is there a single transaction or easier way to do so without having to go into each WO individually?

Thanks for your input.

Regards,

Dean

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Feb 01, 2019 at 10:37 AM

    Hello

    transaction IW38 mass change offers this capabilitiy

    please check

    thanks

    Stephan Bantlin


    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 01, 2019 at 12:55 PM

    Dean,

    You may also want to investigate the use of revisions, which can be used to effectively bundle orders together based on start/end dates.

    See transaction OIOB.

    Paul

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.