Hello all,

I would like to use a statistical project to link maintenance costs to a budget that is maintained in PS. The functionality is all there. i'm now trying to find a proper report.

Currently I'm doubting between 2 options:

Option 1:

CJ30: budgetting in object currency

CJE0: reporting in Controling area currency. Translate to certain currency.

Problem: This always leeds to conversion issues:

budgetted 10000 ---> report shows 9940.

actual cost: 9000 -


> report shows 8340

Option 2:

CJ40 for planning on costelement level

S_ALR_87013543 in object currency

Problem: CJ40 is planned in Controling area currency

What I want is the following:

CJ30 or CJ40 in object currency

Report in object currency where.

Does anybody have an idea how to handle this?

thanks in advance,

Peter

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jun 24, 2010 at 09:48 AM

    hi,

    option 1:in budget profile maintain the budgeting currency as controllingarea currecny. in planning profile change the planning currency as controlling area currency with this you can avoid deviation in reports.

    option 2: create report by copying standard hirechical report and change the report form keyfigure as object currency.

    regards,

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member NAG A C

      NAG,

      Perfect, It's working now. I'm now budgetting in object currency and reporting in object currency.

      Thank you!

      Regards,

      Peter