on 06-23-2010 10:30 AM
Hi All,
We have created Release procedure for PO based on Purchasing Group and we have given the changeability mode as 6. Now everything is working fine except that after releasing the PO, if we make any changes in Payment Terms through ME22N, it is not going to unreleased state.
I have tried with Version Management also. But there is no effect only on Payment Terms.
Please suggest how to proceed.
Regards,
Rosh
Hi
If you want to achive using Version management, yes we can do so.
Use path: SPRO > MM > Purchasing > Messages > Fields Relevant to Printouts of Changes: Create new entry for table: EKKO and field: ZTERM
Regards
Prasanna