We are planning to go for Disaster Recovery for our ECC and PI production servers.

The central SLD is available in the PI DEV server.

I would like to know the pre-requisites or the pain points in building the DR servers for both ECC and PI.

Can anyone please help me on this?

Regards,

Varadhu...

Edited by: Varadhu on Jun 23, 2010 11:04 AM

Accepted Solutions (1)

Accepted Solutions (1)

markus_doehr2
Active Contributor
0 Kudos

The biggest challenge will be the fact to keep both systems in-sync with each other.

What kind of DR are you talking about? Shadow databases? (remote) cluster?

Markus

Former Member
0 Kudos

Markus,

Yes, we are planning to have shadow DB(standby) at the remote site.

Regards,

Varadhu

Answers (2)

Answers (2)

henrique_pinto
Active Contributor
0 Kudos

For an alternative approach on DR based on virtualization techniques, check the results of this project conducted at SAP Co-Innovation Lab: [original link is broken]

Here an article describing more details of the Netapp x Vmware DR solution: http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/1025469e-6d56-2c10-e68a-e09618343...

Screencam: http://www.sdn.sap.com/irj/scn/elearn?rid=/library/uuid/b0f74f51-7056-2c10-ff8d-ddbcb6673fa0

BR,

Henrique.

Former Member
0 Kudos

Dear Markus,

Thanks for ur reply. We have post-poned this activity:(