Planning to happen based on warehouse calendar

Dec 01, 2016 at 02:27 PM

61

avatar image
Former Member

Hi All,

Need your suggestion for below scenario.

In our company planning will happen in APO and from their planned order and subsequent requirements will be pushed to ECC.

We have four to five warehouses and each warehouse got assigned in two to three locations. Components will be issued from warehouse to production line.

Requirement:

Warehouse has own factory calendar (Maintained internally) and working hours and holidays are different from Plant Factory calendar. If any warehouse is not working on specific period then if any planned order falls on those days then system should automatically change the planned date to next working day (based on warehouse working days).

Planned order components we have the storage location from where this has to issue and in Z Table user will maintain the corresponding warehouse for each locations and holiday period.

MRP running at plant level and it will consider only factory calendar which is maintained in Plant.

How to achieve this one.

10 |10000 characters needed characters left characters exceeded
Former Member

Hi Caetano,

Many thanks for your mail.

Is it possible to put any Enhancement / Badi / Exit to reschedule the planned orders after MRP based on entries maintained in Z table.

Now currently user rescheduling the planned orders manually in ECC based on warehouse calendar after planned orders pushed from APO to ECC.

User is ready to run program in ECC and it should consider all planned orders to reschedule automatically instead of manual.

please advise

0
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Caetano Almeida
Dec 01, 2016 at 07:13 PM
0

Hello

From the MRP perspective, I can tell you that it is not possible, since MRP always consider the factory calendar assigned to the plant.


Regards,
Caetano

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Caetano,

Many thanks for your mail.

Is it possible to put any Enhancement / Badi / Exit to reschedule the planned orders after MRP based on entries maintained in Z table.

Now currently user rescheduling the planned orders manually in ECC based on warehouse calendar after planned orders pushed from APO to ECC.

User is ready to run program in ECC and it should consider all planned orders to reschedule automatically instead of manual.

please advise

0
avatar image
Former Member Dec 02, 2016 at 07:26 AM
0

Hi Caetano,

Many thanks for your mail.

Is it possible to put any Enhancement / Badi / Exit to reschedule the planned orders after MRP based on entries maintained in Z table.

Now currently user rescheduling the planned orders manually in ECC based on warehouse calendar after planned orders pushed from APO to ECC.

User is ready to run program in ECC and it should consider all planned orders to reschedule automatically instead of manual.

please advise.

Thanks.

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hello

The following blog provides a list of the BAdIs available in MRP:

https://blogs.sap.com/2013/08/12/badis-for-mrp/

Regards,

Caetano