activity conformation by network

dear all.

my case now is I'd like close project at CJ20N. before I do this actifity I'd like to confirm all actifity in project (cj20n).

I use t-code CN27 to collective confirmation and in this t-code I must fullfill the confirmation requirment one by one ( 1 activity --> one confirmation).

how to confirm by network ??

thanks..

regards,

_eng

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Jun 23, 2010 at 04:24 AM

    Hi,

    As i know that there are not any possibility to confirm because of as per logically work package would be assign to activity itself, otherwise go through BDC(CN27) to update all activity in a single shot.

    SDN Faithfully

    Vishal Kr. Sharma

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 25, 2010 at 03:59 AM

    hi,

    by using this user exist CONFPS01 you can define the default values for confirmation. if default values are maintained

    then you can select the all activities in cn27 and confirm at a time.

    regards,

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 25, 2010 at 04:10 AM

    Hi,

    check in CN25

    Add comment