Subcontractor requirements are seen double on MD04

Former Member
0 Kudos

Hello,

Subcontractor requirements are seen on MD04 in two part, standart and

subcontractor area.

Subcontractor stocks are not included scope of MRP, however,

subcontractor requirements are seen in standart stock and they effect

on standart stock availability, and effect on MRP calculation.

Can you give a suggestion to solve that issue ? These requirements

should only seen in subcontractor area, not in standart area and should

not be taken account in MRP calculation.

Regards,

Onat YILDIZ

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Onat,

A subcontracting requirement will only be displayed in the plant (net requirements) segment in the stock/requirements list if there is insufficient stock provided to the vendor to cover that requirement. Where sufficent stock exists at the vendor, the requirement will only be displayed in the subcontracting segment. This is indicated in the SAP R/3 Documentation as follows:

..

The system does not include requirements of materials provided by a subcontractor (vendor) that are already covered by existing stocks at the subcontractor's plant in the net requirements calculation. The system therefore does not display these requirements in the net.

Each segment(in MD04) stock has an own planning with its own stock and requirements. For each different subcontracting vendor a separate section in the stock requirement list. The subcontracting requirements are then displayed both in the plant stock and in the subcontracting stock. The requirement is covered however in the plant stock. Once the stock

is received the subcontracting requirement is then only displayed in the subcontracting section.

SAP note 550219 has good information also.

I hope this helps!

Former Member
0 Kudos

Thank you very much. Siobhan.

This is very helpful for my question and II will consider this issue on our planing run.