scheduling

Dear PS gurus,

Confirmation parameter OPST: propose dates is tick.

While scheduling eg: Iam having 3activities

1st activity: starting from 18th june having FS relationship with 2nd activity: duration 5days

2nd activity: starting from 25th june

3rd activity:

when i confirm my 1st activity of 5days which is at 22nd june & reschedule it the system takes dates wrt to confirm date of 1st activity. that comes to 29th june to 2nd activity.

Is this related to confirmation parameter.

Regards,

AHS

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jun 22, 2010 at 05:27 AM

    Let me elaborate this in a better way:

    Assume we have below situation :

    Activity 1, start date 18/06/2010

    Activity 2, start date 25/06/2010 - FS relation ship with Activity.1 - 5 days

    In case Activity 1 confirmed date = 22/06/2010, after rescheduling from within transaction CJ20N, system takes this date into account and as a consequence of that, Activity 2 start date becomes 29/06/2010

    Rescheduling from CJ20N transaction should act in the same way as transaction CAT5 with the option "Transfer without dates"'.

    Regards,

    AHS

    Add comment
    10|10000 characters needed characters exceeded

    • Propose dates will not affect your re-scheduled date...If you want to know why system is considering the confirmed date during calculation of scheduled date, then, I would suggest you to read SAP HELP files, explanation is provided in it.