Hello Dears,
Could you please explain with example for lot size,replinesh to maximum stock level.
Appreciate early action
Hi Sridevi
This all will come in consumption based planing
CBP work with Reorder point , Forecast based and time based requirement.
In Reorder point system will work stock levels and lot size . if the system stock below the minimum stock levels system generate the indents.
if lot sixe fx - fixed qyt
ex- lot for lot order qyt
hx- maximum stock levels system check the qty
Regards
laxman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there,
http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d3f9344af11d182b40000e829fbfe/frameset.htm
You may also go to transaction OMI4 (MRP Lot Size).
Maximum stock level is used during MRP excution with lot size procedure
Please see F1 help documentation of field..
Maximum stock level
Quantity of the material in this plant that may not be exceeded.
Use
In materials planning, the maximum stock level is used only if you have
chosen Replenish to maximum stock level as the lot-sizing procedure;
that is, you have entered HB as the lot size key.
Procedure
Enter a value if you have chosen Replenish to maximum stock level as the
lot-sizing procedure.
Please see attached note 51576 MD01: MRP type V1/V2: reorder point w.
for more information.
Hope this helps,
Kind Regards,
Matthew
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.