Hi Gurus,
Just would like to briefly understand, how I can make use of the WBS Element in the Production Order (Assignment tab) to use as cost settling for a production order? How do i automate the WBS Element in the production Order for a set of given parameters? Is there a config I can use to set a profile?
I have a scenario here as below:
I have various types of production orders:
PO 1 = Production A
PO 2 = Production B
PO 3 = Production C
And for each of the above, I will individually have a WBS Element.
PO1 - WBS Element A
PO2 - WBS Element B
PO3 - WBS Element C
And WBS Element A, B and C is a Level 2 WBS Element which are tied to WBS Element Z (Level 1 WBS Element), which will be settled to a project.
Appreciate your kind feedback on the above on how I can make it work by settling the cost to the WBS Element.
Thanks.