Project Budget Mandatory

Hi Experts ,

I am looking at functionality where , the user should not raise the Purchase Requisitions without prior allocation and release of budget .

Currently users are able to create the Purchase requisitions while the status is"CRTD " and the Projects are not Budgeted .

I am aware of using user status and more of looking at a functionality without using user status .

Appreciate the experts suggestions.

Kind Regards

Judy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jun 20, 2010 at 11:36 AM

    If you dont want to user user status, then activate availability control (CJBV) immediately after creating project...since the budget is 0, the system wont allow you to create PR or PO...without providing sufficient budget.