Hello Friends,
I am facing a strange situatiion in my PM order. The cost calculaton is happening on DURATION value instead of WORK
i.e
Planned cost = DURATION * ACTIVITY RATE instead of WORK * ACTIVITY RATE.
Appreciate if some one could help on this issue... and how to resolve this.
Thanks,
Sajjad
Sajid,
Check and make sure that you have maintained the right formula for capacity (SAP008 in Other formula) and Scheduling( SAP004 in Other formula) in the work center associated to that operation for the plant.
Regards
Narasimhan