PM Order : Planned cost calculation happening on DURATION value !!

Hello Friends,

I am facing a strange situatiion in my PM order. The cost calculaton is happening on DURATION value instead of WORK

i.e

Planned cost = DURATION * ACTIVITY RATE instead of WORK * ACTIVITY RATE.

Appreciate if some one could help on this issue... and how to resolve this.

Thanks,

Sajjad

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jun 19, 2010 at 01:26 PM

    Sajid,

    Check and make sure that you have maintained the right formula for capacity (SAP008 in Other formula) and Scheduling( SAP004 in Other formula) in the work center associated to that operation for the plant.

    Regards

    Narasimhan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear Narasimhan, - we had manitained a wrong Formula key for costing. When it was replaced by SAP008 it was working fine. Thanks for your support