Hello,

Need your kind advice please. This is the situation:

1. We have three clients in Dev.

2. They are (for eg), client 6 for all config, client 100 for testing in Dev and client 1 which was temporarily created for a project for both config as well as testing for that project only. To make matters complicated, both client 1 and 100 point to separate sets of applications.

3. After the project got over, client 1 was left like that. As a result several people over the last one year kept making config changes there.

4. End result is that a group of users used client 6 for making config changes and then moved the TR to client 100 for testing, before moving them to QA. Another group of users used client 1 to make the config changes as well as testing them there before moving the TR to QA.

5. Now, we have to delete either client 1 or client 100.

6. Our customer wants to have same data in the corrected Dev client as is there in Prod.

7. Doing a remote client copy would erase everything that is presently there on the target client. That would mean that either the applications running on 100 or 1 would get erased.

8. What would be the best way to manage the situation here?

9. Customer doesnt want to user Loadrunner to create data for testing in Dev. They want the data from Production to be there in the Dev client.

10. Assuming, disk space is not an issue, how do we best manage the situation?

regards,

Suvarghya

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Jul 01, 2010 at 01:28 PM

    Hi Suvarghya,

    I have no idea what kind of data you want to copy from PRD to DEV.

    As I know, there are many remote client copy profile for you to slect in SCC8.

    SAP_USER-> User Master

    SAP_CUST -> Customizing + Initialize& Recreate

    SAP_UCUS-> User Master + Customizing + Initialize& Recreate

    SAP_UAPP -> User Master + Customizing + Master & trans.data + Initialize& Recreate

    SAP_ALL-> User Master + Customizing + Master & trans.data + Initialize& Recreate + Variants

    SAP_CUSV-> Customizing + Initialize& Recreate + Variants

    SAP_UCSV-> User Master + Customizing + Initialize& Recreate + Variants

    SAP_EXBC*-> User Master + Customizing + Initialize& Recreate + Variants + Client-indep. tables

    SAP_EXPA*-> User Master + Customizing + Master & trans.data + Initialize& Recreate + Variants + Client-indep. tables

    SAP_EXPC*-> Customizing + nitialize& Recreate + Variants + Client-indep. tables

    You can also refer to the following notes for details:

    552711 FAQ: Client copy

    24853 CC-INFO: Client copy, functionality

    19574 CC-ADMIN: Controlling data selection during client copy

    With Best Regards

    Julia

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 01, 2010 at 01:49 PM

    Survaghya,

    If you copy your prod system to your dev system you will loose all your version management and you wont be able to make changes to the system. Else you need to back TADIR table and other important tables.

    Just check if you get any information from SAP Marketplace about system copies.