on 06-18-2010 7:58 AM
Dear Friends,
We have PO Release Strategy by A , B, C.
we want to restrict if PO Released by A and B then A cant unrelase the PO wihtout B Release and the same with B & C
at present if PO released A , B and C ... A can unrelease the PO and amending the same...
kindly advice the same
awaiting for ur kind reply
Thanks
Rajesh G
Hi Rajesh,
In standard, the revoke option will be available for either of the releasers who had released the PO. So to have the control based upon your requirement, only way is to do it through user exit.
Pls get the help of ABAPers for imlementing your own logic.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
>
> Dear Friends,
>
> We have PO Release Strategy by A , B, C.
>
> we want to restrict if PO Released by A and B then A cant unrelase the PO wihtout B Release and the same with B & C
>
> at present if PO released A , B and C ... A can unrelease the PO and amending the same...
>
> kindly advice the same
>
> awaiting for ur kind reply
>
>
> Thanks
>
> Rajesh G
This is only possible through Release prerequistes in each release strategy...if possible then let us know what your present Release prerequistes looks like....
Regards,
Indranil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your kind reply. our Release Indicator as follows
1 Cannot be changed
2 Changeable, no new determination of strategy
3 Changeable, new release in case of new strategy
4 Changeable, new release in case of new strat. or val. change
5 Changeable, new release if new strategy/outputted
6 Changeable, new rel. if new strat. or value change/outputted
Changeable, new release in case of new strategy
Release code
50 A 0
51 B 0
52 C 9
if i am putting 51 B 1 then after release B PO not coming to C for release.
please advice how can to get
regards,
Rajesh G
>
> Thanks for your kind reply. our Release Indicator as follows
>
> 1 Cannot be changed
> 2 Changeable, no new determination of strategy
> 3 Changeable, new release in case of new strategy
> 4 Changeable, new release in case of new strat. or val. change
> 5 Changeable, new release if new strategy/outputted
> 6 Changeable, new rel. if new strat. or value change/outputted
> Changeable, new release in case of new strategy
>
> Release code
>
> 50 A 0
>
> 51 B 0
>
> 52 C 9
>
>
> if i am putting 51 B 1 then after release B PO not coming to C for release.
>
> please advice how can to get
>
> regards,
>
> Rajesh G
Sorry but I am a bit confused Rajesh...actually as per your initial issue we had asked for your Release pre-requsite...how it has been maintained in your release strategy...
Cn you please let us know what is your actual issue?
Regards,
Indranil
your requirement is possible by maintaing pre requistes. so go to prerequistes and maintin as you required
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You have to adjust the pre-requisits in the release strategy so that the requirement is fulfilled.
Satish Purandare
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.