PO not changable after Release

Former Member
0 Kudos

Dear Friends,

We have PO Release Strategy by A , B, C.

we want to restrict if PO Released by A and B then A cant unrelase the PO wihtout B Release and the same with B & C

at present if PO released A , B and C ... A can unrelease the PO and amending the same...

kindly advice the same

awaiting for ur kind reply

Thanks

Rajesh G

Accepted Solutions (1)

Accepted Solutions (1)

former_member712038
Contributor
0 Kudos

Hi Rajesh,

In standard, the revoke option will be available for either of the releasers who had released the PO. So to have the control based upon your requirement, only way is to do it through user exit.

Pls get the help of ABAPers for imlementing your own logic.

Regards,

Answers (3)

Answers (3)

Former Member
0 Kudos

>

> Dear Friends,

>

> We have PO Release Strategy by A , B, C.

>

> we want to restrict if PO Released by A and B then A cant unrelase the PO wihtout B Release and the same with B & C

>

> at present if PO released A , B and C ... A can unrelease the PO and amending the same...

>

> kindly advice the same

>

> awaiting for ur kind reply

>

>

> Thanks

>

> Rajesh G

This is only possible through Release prerequistes in each release strategy...if possible then let us know what your present Release prerequistes looks like....

Regards,

Indranil

Former Member
0 Kudos

Thanks for your kind reply. our Release Indicator as follows

1 Cannot be changed

2 Changeable, no new determination of strategy

3 Changeable, new release in case of new strategy

4 Changeable, new release in case of new strat. or val. change

5 Changeable, new release if new strategy/outputted

6 Changeable, new rel. if new strat. or value change/outputted

Changeable, new release in case of new strategy

Release code

50 A 0

51 B 0

52 C 9

if i am putting 51 B 1 then after release B PO not coming to C for release.

please advice how can to get

regards,

Rajesh G

Former Member
0 Kudos

>

> Thanks for your kind reply. our Release Indicator as follows

>

> 1 Cannot be changed

> 2 Changeable, no new determination of strategy

> 3 Changeable, new release in case of new strategy

> 4 Changeable, new release in case of new strat. or val. change

> 5 Changeable, new release if new strategy/outputted

> 6 Changeable, new rel. if new strat. or value change/outputted

> Changeable, new release in case of new strategy

>

> Release code

>

> 50 A 0

>

> 51 B 0

>

> 52 C 9

>

>

> if i am putting 51 B 1 then after release B PO not coming to C for release.

>

> please advice how can to get

>

> regards,

>

> Rajesh G

Sorry but I am a bit confused Rajesh...actually as per your initial issue we had asked for your Release pre-requsite...how it has been maintained in your release strategy...

Cn you please let us know what is your actual issue?

Regards,

Indranil

Former Member
0 Kudos

your requirement is possible by maintaing pre requistes. so go to prerequistes and maintin as you required

Former Member
0 Kudos

Hi,

You have to adjust the pre-requisits in the release strategy so that the requirement is fulfilled.

Satish Purandare