cancel
Showing results for 
Search instead for 
Did you mean: 

No capacity requirements were found in the evaluation period

Former Member
0 Kudos

Hi gurus,

I am using CM25 and im trying to do a capacity evaluation but i keep on getting this message "No capacity requirements were found in the evaluation period" and "No work centers or orders were found" no matter what overall profile i keep on getting the same errors.

What do i need to set up or configure in order to make this work..

Thank you so much!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Make sure that the control key used for the operation allows generation of requirement records.( Use the drop down of the control key to check whether "Determine Capacity Requirements" has been selected for this).If this is not set, Make sure to set them using menu path SPRO > PM> Orders > Settings for order types> Control key> Define control key.

Also make sure that the Work center has the right formula associated to it for generation of capacity requirements(SAP008 for capacities and SAP004 for scheduling in the Other formula field).

These two settings should result in generation of capacity requirement records for the work center against the order.

Regards

Narasimhan

Former Member
0 Kudos

Hi,

I'm having the same problem

using CM25 and im trying to do a capacity evaluation but i keep on getting this message "No capacity requirements were found in the evaluation period" and "No work centers or orders were found"

and read your suggestion...

step 1, (which I did it)

I selected the "Determin Capacity Requirement" for the control key.

Step 2,

Also make sure that the Work center has the right formula associated to it for generation of capacity requirements(SAP008 for capacities and SAP004 for scheduling in the Other formula field).

where do you do this? Can you please give me more detail...

After I did step 1, the problem is still there....

using CM25 and im trying to do a capacity evaluation but i keep on getting this message "No capacity requirements were found in the evaluation period" and "No work centers or orders were found"

Thank you,

Sam

Former Member
0 Kudos

Thanks Narasimhan! it worked

Answers (2)

Answers (2)

peter_atkin
Active Contributor

And make sure you have time against operations for the relevant CM25 date range

PeteA

Former Member
0 Kudos

Hi Experts,

I have the same problem too when execute tcode CM24, "no capacity requirement were found in the evaluation period" , I did the first and two steps but the message still show.

Is there any documentation how to solve this?

Thank you experts,

Rgds

Sonia Helena

jogeswararao_kavala
Active Contributor
0 Kudos

Hello Sonia,

You won't (shouldn't) get responses if you post your query like this in a closed thread. So, please post a new query (Start a new discussion). If needed give reference to this link.

Good luck

KJogeswaraRao