cut over activities in PM

Hi experts,

Is there any cut over activity in PM module? Can any one please give details if yes.

rgds

rajib

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Jun 16, 2010 at 04:27 AM

    Hi,

    1) Preventive Maintenance Plan scheduling date is the major cutover activities for PM.

    2) For Spares procurement and Service Procurement cutover activies, consult with MM.

    Regards,

    KBU

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 16, 2010 at 07:34 AM
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 16, 2010 at 12:09 PM

    Hi

    here is list of cut over activities

    - Selection screen variants (e.g. IW38)

    - Report display variants (e.g. IW38)

    - Strategies for maintenance plans

    - Number ranges (manual transports)

    - Data for non-customisable Z tables

    - Quickview/ABAP Query reports

    - Transfer open orders/notifications from legacy system to SAP

    - Schedule maintenance plans from start-date of go-live

    - Classes & Characterisitics (you can ALE these from one system to another)

    - Schedule background jobs (e.g. IP30, custom developed reports/programs, etc)

    - SmartForm fonts

    - and initial measuring documents

    regards

    Jitender