I have created a material GLASS and have set the inspection type to 06 and 10.There is sufficient stock in Customer Consignment.

I want the stock to move to QI from Ciustomer consignment and the system should not allow the user to do pgi until the stock moves from QI Consignment to Customer Consignment Unrestricted so that PGI can be done after that.

Plzzzzzz can someone guide me in mapping the above requirement.

Q2.I want to enter the quality certificate no in my delivery document.The system should check that the QC No exists or not.If it doesn't it should display an error message.How to configure this.

Someone plzz help.

Regards.

Saurav M.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jun 14, 2010 at 02:26 PM

    Q1) First of all, I dont know why you want the customer consignment stock should be moved to quality. In reality, it should have been vice versa. That is before despatching, quality inspection should have taken place.

    Nevertheless, to address your requirement, you need to create a return order for which, you should have a new schedule line category in VOV6 where you assign movement type 655.

    Based on the (ideally it is pick up order) return order, you have to create a return delivery and post the goods return so that the stock will be posted to QI for their clearance.

    Q2) Try with V50S0001 - User Exits for Delivery Processing

    thanks

    G. Lakshmipathi

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 30, 2010 at 09:55 AM

    Thanks for your response.