on 01-29-2019 4:50 PM
Hi Team,
I am in a situation where I need the budget and budget reports based on cost center rather than the GL Accounts. As of my understanding the budget is based on GL accounts and we add cost centers and their budget for each GL account. But I need is only cost centers, their budget and actuals.
Regards,
Krish
I don't know if this helps, but I did the following:
I created a scenario for each cost center. Then, when defining the budget, I selected the manual method and budgeted the amounts for each month.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Krishnam,
Unfortunately the Budget can only be assigned to the accounts not to the cost center. 😞 Try creating the custom forms to achieve this requirement.
Thanks
Dinesh PN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krishnam,
Unfortunately there is no separate budget screen for cost center alone. But you can assign your list of cost center for each account in Budget screen itself.
1.Financial - Budget Setup - Budget Scenarios (Create your budget name here)
2.Financial - Budget Setup - Budget (Select your scenario) - OK
3.Choose the desired account - Input the budget amount on selected account - Right Click Add cost center assign the value to that cost center
- Update
Note: Before start entering your Amount select your Dimension on the right top corner.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.