Dear Guru,
In one of plant i have a typical problem.
Whenever system does the forward scheduling for the external procurement , system does not takes Todays date (MRP Run date).
System simply sifted the requirement date by 30 days. and scheduled accordingly. In the expection message system shows the correct requirement date.
Please help.
Regards,
Sanjay