on 06-11-2010 4:31 PM
Hi
The customer is using SBO 2007 Sp 1 PL05.
When Runnig the RMP the Oder multiple is not include??
Planning Method - MRP
Procurement Method - BUY
Order Multiple - 6
Minimum Order Qty. - 6
The recommendation is not a multiple of 6, do i have to setup someting else ?
Thanks
Yves
I found, the order multiple is link t the lead time, so if the lead time is not met, order multiple is ignored
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi .....
Are you mentioning the same multiple while running MRP wizard also?
Regards,
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check whether the warehouse assigned is Nettable. If sales order to be considered in MRP, mark Consume Forecast(if you have defined a forecast) in SO, also in General Setting, Inventory Tab mark Consume Forecast
Regards
ShriX.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.