Charge the material cost to another activity

Hi all,

How it is possible to charge the material cost to another activity?

The material has GR for the activity A but we require the cost in the activity B (Activities are in same network)

Is it possible to charge the material to this activity (Without PR creation).

Regards, Madhusudan Patil

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jun 12, 2010 at 05:20 AM

    hi,

    txn kb15n select the scrn var as wbselement/network and enter the sender wbse,network,activity no,costelement and amount.

    enter the data for receiver also. with this you can transfer the material cost from one activity to other.