Hi Experts,
While i am trying to transfer material from Valuated project stock to Non valuated project with T.Code MB1B movement type 415 'Q', I am getting following error.
WBS element has different inventory valuation
Message no. CN769
Diagnosis
The project definition for WBS element only allows the following stock control:
No project stock
No project stock with defined valuation M
' ' = non-valuated project stock
'M' = valuated project stock
System Response
Account assignment not possible.
Procedure
Change the settings for the project stock in the project definition (Control tab) or use a suitable WBS element.
Kindly suggest me how to trafer material from Non valued project stock to valuated project stock.
Regards