I would like to reopen an unsolved issue of 2014:
In CMP2 we allocate/plan employees to PS-activities - with specific hours per day/week.
In CAT2 the employees create confirmations of their actual hours spend at the activities.
We would like to have a report where the Project Manager can see the planned versus actual hours spend per employee. (We could build a report by informations in the database tables from CMP2/CMP3 and CAT2/PS confirmation. But - the problem is, that when an activity get status Tecnically completed or Closed - then the CMP2/CMP3 informations are deleted from the database tables and can no longer be used.)
I hope someone has faced same request, have solved the challenge and would kindly share the solution,