Material Cost Estimates

39 Views

HI GURUS

Product A Details

Material type = ZXXX ( customized ) , Plant = 1500

Bom Componet = G & H ( where product G is non - valuated , no costing view maintained with material type = Z111, while H is valuated product )

Production type = PP-PI

Product B Details

Material type = ZYYY ( customized ) , Plant = 2000

Bom Componet = k & s ( where product k is non - valuated , no costing view maintained , with material type = Z111 while S is valuated product )

Production type = Repetitive Manufacturing

we are already Creating material cost estimates for material A. through ( Ck11N ) successfully . with a Costing varient = ZC11 .

also while creating cost estimates , in costing structure ( explorer ) , Non-valuated material G is not being shown there.

But when we create cost estimate for for material B throgh CK11N . with costing varient ZC11. it gives error

" No price could be determined for material \ batch K / plant 2000. Non-valuated material K is shown in costing structure.

How we can restrict the Non-valuated material not being showing in costing structure in case of B material. as it is being happen in case of material A.

thanks \ thomas