Processing time in production order is different from routing

Dec 01, 2016 at 12:56 PM

186

avatar image
Former Member

Normally processing time in production order for one operation is equal to the machine time in routing*order qty and set up time is equal to the setup time in routing. But in our system, we find that 1 production order has some issue. The setup time is 0 and the processing time is 840 mins, which can not match with routing time.

capture.jpg (78.0 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Caetano Almeida
Dec 01, 2016 at 07:51 PM
0

Hello

Data can be changed directly in the production order after the routing is read, therefore, you cannot always compare both values.

Regards,

Caetano

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Dec 02, 2016 at 02:47 AM
0

Hi

Kindly check the setup and processing formula maintained in the work center master for the work center corresponding to operation number 0010.

Regards,

Gokul