Processing time in production order is different from routing

Normally processing time in production order for one operation is equal to the machine time in routing*order qty and set up time is equal to the setup time in routing. But in our system, we find that 1 production order has some issue. The setup time is 0 and the processing time is 840 mins, which can not match with routing time.

capture.jpg (78.0 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Dec 01, 2016 at 07:51 PM

    Hello

    Data can be changed directly in the production order after the routing is read, therefore, you cannot always compare both values.

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 02, 2016 at 02:47 AM

    Hi

    Kindly check the setup and processing formula maintained in the work center master for the work center corresponding to operation number 0010.

    Regards,