on 06-10-2010 10:45 AM
hi all,
I have defined 2 splits in the work center. Operation split is ticked in routing.
When I create an order for 10 units , it is getting split as 7.5 and 2.5. i would like to know where this proportion is defined if it can be ?
Regards,
Yogesh
Yogesh,
In the operation details you need to activate the Required Splitting indicator and maintain the minimum time for splitting, based on this system calculates the number of splits by dividing the processing time for the operation by the minimum processing time.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear ,
It is based on the Formula Key(SAP001,SAP002,SAP003-OPK3/OP7B ) maintained in Work Centre -Capacity Tab and routing operation -Splitting Allocation in operation -co02-production order -operation overview-select the operation -Capacity Req.assingment -Split qty .
Regards
JH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.